Materials and costs
Everything to buy for the basement, grouped by the order the work happens. Materials only, about $4,650–$7,585 for a DIY finish.
Quantities come from the new design in the 3D model, with waste included, not from a tape measure. Prices are ballpark big-box retail as of November 2026, shown low–high, so check them before buying.
Phase 1 Prep$575–$875
Room 2's carpet and drop ceiling come out, 8′-7″ of the dividing wall comes out for the pass-through, and the slab gets a moisture check before anything is covered.
| Item | Qty | Est. cost |
|---|---|---|
| Dumpster rental, 10 ydCarpet, drop ceiling, partition | 1 | $350–$550 |
| Contractor bags, 42 gal | 1 box | $25–$35 |
| Moisture test kitSlab and walls, before foam | 1 | $15–$40 |
| Concrete crack filler | 2 tubes | $20–$30 |
| Self-leveling underlayment, 50 lbOnly for low spots | 2–3 bags | $120–$150 |
| Plastic sheeting and painter’s tapeMasking for the ceiling spray | 1 roll + 3 | $45–$70 |
Phase 2 Framing and insulation$1,315–$1,825
2″ rigid foam glued to the block, a 2×4 wall in front of it, on a pressure-treated plate over a sill gasket.
| Item | Qty | Est. cost |
|---|---|---|
| 2″ XPS or polyiso foam, 4×813 walls, 2 rim joist bays | 15 sheets | $675–$975 |
| Foam-safe construction adhesive | 7 tubes | $49–$63 |
| Foam seam tape | 1 roll | $15–$25 |
| Spray foam cans | 6 | $48–$60 |
| 2×4×8′ studsOr steel studs, about the same | ~100 | $350–$450 |
| Pressure-treated 2×4×8′ bottom plate | 9 | $54–$72 |
| 2×4×8′ top plate | 9 | $32–$41 |
| Foam sill gasket, 5½″ × 50′ | 2 rolls | $24–$36 |
| Concrete fasteners | 1 box | $30–$45 |
| Framing screws or nails, 3″ | 5 lb | $30–$45 |
| 2×6×10′ door header | 1 | $10–$14 |
Phase 3 Drywall$480–$630
About 645 sq ft of wall: the insulated exterior walls, both sides of the utility closet wall, the box column and the beam box. No ceiling board.
| Item | Qty | Est. cost |
|---|---|---|
| Mold-resistant drywall, ½″ 4×8Exterior walls | 14 sheets | $238–$308 |
| Drywall, ½″ 4×8 | 9 sheets | $117–$144 |
| Drywall screws, 1¼″ | 5 lb | $25–$35 |
| Paper joint tape | 1 roll | $5–$8 |
| All-purpose joint compound | 2 boxes | $36–$44 |
| Setting compound | 1 bag | $15–$20 |
| Corner bead, 8′ | 10 | $40–$60 |
| Mesh tapePatching Room 2’s old walls | 1 roll | $6–$9 |
Phase 4 Paint$595–$965
Black dry-fall sprayed on the open ceiling (best done before the drywall goes up), then primer, gray walls and white trim.
| Item | Qty | Est. cost |
|---|---|---|
| Flat black dry-fall ceiling paint | 5 gal | $150–$250 |
| Airless sprayer rental | 1 day | $90–$130 |
| PVA drywall primer | 3 gal | $75–$111 |
| Wall paint, eggshell gray | 5 gal | $180–$300 |
| Trim paint, semi-gloss white | 1 gal | $35–$60 |
| Rollers, covers, brushes, liners | 1 kit | $40–$70 |
| Paintable caulk | 6 tubes | $24–$42 |
Phase 5 Flooring$1,050–$2,065
About 415 sq ft of waterproof wood-look plank, bought as about 460 with waste. The utility closet stays concrete.
| Item | Qty | Est. cost |
|---|---|---|
| Vinyl plank (LVP/SPC)Biggest swing in the budget | ~460 sq ft | $920–$1,840 |
| 6-mil poly vapor barrier, 10×50′Skip if the plank has a pad and you use combo underlayment | 1 roll | $35–$60 |
| Seam tape | 1 roll | $8–$12 |
| T-molding or reducerCloset doors | 2 | $50–$80 |
| Stair-bottom transition | 1 | $30–$60 |
| Expansion spacers | 1 pack | $8–$12 |
Phase 6 Trim and doors$635–$1,225
Baseboard and casing, the 4′ double door into the utility closet and the 28″ under-stair closet door.
| Item | Qty | Est. cost |
|---|---|---|
| Baseboard | ~110 ft | $132–$275 |
| Door and window casing | ~55 ft | $55–$110 |
| Window stool, egress | 1 × 4′ | $15–$30 |
| Prehung double door, 2 × 24″ | 1 set | $250–$450 |
| Door, 28″ | 1 | $120–$250 |
| Knobs: dummy pair and passage | 1 + 1 | $40–$80 |
| Finish nails, 2″ and 1¼″ | 2 boxes | $16–$24 |
| Shims | 1 bundle | $5–$8 |
Not in these numbers
- The egress window: cutting the foundation, the window, the well and the ladder. That's usually hired out and quoted separately.
- Electrical: recessed lights, outlets, switches and wire.
- Plumbing: capping the laundry sink lines.
- Built-ins: the open shelves and base cabinets, the crawl-space shelf bay and its sliding doors, the under-stair drawers and the corner bar.
- Furniture and gym equipment.
- Tools beyond the sprayer rental, plus permits and labor.
Still to check with a tape and the inspector: the real floor-to-joist height at each wall, the plank's box size, and local rules for basement wall insulation.